Release Planning and Honest Bidding: Pricing Software Without Guesswork.
When a prospective client contacts outsourcing partners for software development, they have a crucial question. Beyond the usual "get to know you" questions, this question stands out.
“How long will it take to build my software and how much money will it cost?”
Outsourcing engagements often turn into nightmares, and this is where it begins. Buyers often realize it months after signing contracts.
To explain this, I’ll use an analogy that’s near and dear to my heart, having just lived through it: remodeling a house my wife and I bought in California. We went into purchasing the home with our eyes partially open… we knew there was work to be done, but we were not aware of how much work or how much it would cost.
We met with a couple of contractors for bids. They listened to our needs and took notes for their quotes. We chose a contractor based on cost and trust, which was mainly misplaced. He promised to complete the work in five weeks, starting the Monday after our agreement meeting.
That marked the final good day we had while renovating our house, and we hadn't even started hammering the first nail, so to speak.
Without belaboring details, a couple of behavior patterns emerged quickly and persisted throughout the project:
Over-promising and under-delivering… this mostly applies to having workers actually show up to work on the dates and times to which they committed. The two-week unannounced vacation our contractor had planned before even bidding on our project was the most egregious violation of this trust.
Padding invoices due to "scope changes" was another issue. Our contract was based on a spreadsheet detailing tasks with associated prices. As an example, we had agreed to replace all the interior doors. However, when we received the first invoice, there was an additional charge for "door installation." When we questioned the contractor, he explained that his bid covered removing the old doors but not installing the new ones, hence the overage charge. Absurd, as any reasonable person should be able to assume that replacing doors would include removal and installation. In short, he found a “loophole” in the contractor and exploited that to pad an invoice.
The quality of the work was subpar. For example, we paid to replace all the insulation in the crawl space under the house and to clear out debris left from previous construction. However, upon inspection, we discovered that they had only replaced the insulation in the area near the crawl space entry point. They did just enough to give the impression that all the insulation had been replaced, even though it wasn't.
On the day we settled our finances with the contractor, we confronted him about the second point above: padding invoices. His blatant response was, "If I had told you the actual price when I was bidding, I wouldn’t have won the business."
Legally, I might have recourse against the contractor. However, the process, whether my wife and I win or lose any claim we pursue, is bound to be painful.
From an ethical standpoint, what this contractor did is as abhorrent as it is common. My recourse ethically is clear. That contractor will never again work on my property - or that of anyone who asks me for a contractor recommendation.
The irony is that this engagement simply didn’t have to go this way. My clearly stated request to this contractor from day one was simple: do your work with integrity and treat my house as if it were yours. Yeah, right… This contractor never intended to honor that request because they have no integrity.
Which returns me to the topic of software development and outsourcing. This business is surprisingly similar to the home remodeling business. During the first 20 years of my career, I painfully observed that technology outsourcers, including software development firms, often engage in the same practices our remodeling contractor did when hiring various outsourcers to do work.
And this behavior usually starts during the bidding process, just as it did with the remodel.
The prospective client provides “requirements” for their software application to the outsourcing companies selected to submit bids. The format of the requirements we receive varies widely. It can be as brief as a 10-minute verbal overview or a mix of presentations and documents showing a high-level concept. Sometimes, we get a traditional, detailed Product Requirements Document (PRD) in the waterfall style.
The rub is that, for an agile software development firm to accurately estimate the development of a software product, we must have an agile software development plan. That release plan includes:
User personas and “user stories” (feature requirements defined through the lens of the person using or benefiting from each feature. Stories don't have to contain all the acceptance criteria or detailed use cases. However, they must be clear enough for developers to understand the scope and estimate the implementation accurately.
Information architecture that describes how different objects in the system relate to one another.
User experience definition, including user journeys and wireframes of key features and screens.
Many outsourcing firms tend to rely solely on the information provided by prospective clients. They create estimates and bids without fully understanding the project's scope. When a vendor operates like this, which I believe is a low-integrity approach for the reasons mentioned above, their estimates are likely to be incorrect. This is often the start of what can become an outsourcing nightmare.
When a prospective client approaches us, and we confirm the opportunity is genuine, not just exploratory, our team starts building the release plan mentioned earlier. We do this without charging the client for the "discovery" phase. This phase usually takes between 60 and 150 hours. It involves a diverse team including a product manager, requirements analyst, user experience and interface designer, technical architect, and project manager. This "bid team" works together to create the release plan and develop the most precise estimate before we submit our bid.
There are several reasons:
Our company lives and works by a set of values: integrity, work ethic, craftsmanship, innovation, and growth mindset. Being at the top of our list means we never give clients incorrect estimates due to a lack of effort. We always do the necessary work to ensure our estimates are accurate.
CodeStringers is a boutique outsourcing firm, deliberately small-scale for quality. Our senior executives, often including myself, lead all client projects, typically as the product manager. This approach brings great value to clients who need help turning business needs into software plans. Creating the release plan demonstrates the worth of a boutique partner. It also helps build rapport and trust with our clients.
Successful relationships are built upon honesty and a genuine interest in mutual success. Submitting a bid that is known to be incorrect is, in a word, a lie.
Let us earn your trust and business. First, we'll confirm your commitment and funding for software development. Then, we'll assist in creating your release plan for a precise estimate. Our process is transparent. We show you the release plans, detail the effort for each feature, the development timeline, and the cost. Our goal is for you to make an informed decision.
CodeStringers
In a no-risk discovery we look at your CRM, finance and operations systems and who owns each part, and show what a connected system would do differently. You pay only if you proceed. Or see how we approach it.
More on the same problem:
Zoho CRM Custom Views Explained: Criteria, Sharing, and Sorting Without the Guesswork (article)
Mental Health Practice Management Software: Build vs. Buy (An Honest Take) (article)
Scale Without Staffing Increases (video)
Release planning is the work of defining what a first version of a product will do, who it serves and roughly how long it takes to build, before development starts. It produces user personas, user stories, an information architecture and wireframes of the key screens. Those artifacts let a team estimate each feature instead of guessing from a short brief, and they give the buyer a plan to hold the vendor to.
A bid made without a release plan is a guess, and the vendor usually knows it. Once work starts, every feature the brief did not spell out becomes a change order, and the price climbs past the honest bids the buyer rejected. The buyer also pays in time, because disputes about scope stall the build. A higher bid grounded in a plan is often the cheaper one over the life of the project.
For a typical product build, release planning takes a few weeks of part-time work from a small group: a product manager, a requirements analyst, a designer, an architect and a project manager. The page describes 60 to 150 hours as a typical range. The time depends on how many stakeholders need to be heard and how much of the product already exists on paper.
A usable release plan has user personas and user stories clear enough to estimate, an information architecture showing how the objects in the system relate, and user journeys with wireframes for the key screens. It also carries an effort estimate per feature, a development timeline and a cost. If a vendor cannot show you those pieces, the estimate behind the bid is not grounded in anything.
Ask what the estimate is based on, whether they wrote user stories or worked from your brief, and what happens to the price and date when a story turns out larger than expected. Ask to see the feature-level breakdown rather than one total. Ask who on their side owns the plan during the build. Vendors that did the planning answer quickly; vendors that guessed change the subject.